| # | Input | Type | Used in step |
|---|---|---|---|
| I-1 | Sales Order (lines per size, carrying the ship-to Country) — Plan qty may exceed Remaining, the excess becomes Common Stock | Document — Sales module | Start → Create Plan: select SO lines |
| I-2 | Internal Production Request | Internal document | Create Plan: select SO lines |
| I-5 | Country — Area field (Area of the ship-to Country on the SO line) | Master data | Step 2: group SO lines into Big Plans (Area is part of the grouping key) |
| I-3 | Item · Routing · Routing Mapping (the item's default routing + alternative routings) | Master data | Step 3 Review: pick a Routing for each Work Order |
| I-4 | Machine · Capacity Calendar | Master data | Calculate Plan From / To from lead time, check Capacity |
| Step | Role | Screen · UI button |
|---|---|---|
| Open the Create Plan wizard | Planner | Master Plan · Plan List · Create Plan |
| Filter plans by Area (view only, not a business step) | Planner | Master Plan · Plan List · field Area outside the grid (All / Europe / Asia / America) · column Area |
| Select SO size lines · Enter Plan Qty per line | Planner | Master Plan · Step 1 · Select SO Lines |
| Select Plan Month | Planner | Master Plan · Step 2 · Item Lines · field Plan Month |
| Group SO lines into Big Plans · Calculate Common Stock | System (auto) | Master Plan · Step 2 · Item Lines (one row per Big Plan) |
| Pick a Routing for each Work Order | Planner | Master Plan · Step 3 · Review & Create (the Routing field of each WO) |
| Calculate Plan From / To from lead time · Flag Over capacity (warning only) | System (auto) | Master Plan · Step 3 · Review & Create |
| Create Master Plan | Planner | Master Plan · Step 3 · Create Plan |
| View the plan's Work Orders (view only, not a business step) | Planner | Master Plan · Plan List · column WO with an expand icon (1 plan → n WOs, with Process · Progress · Status); Plan Details › tab Work Orders › Process view (tree WO → processes, status and quantity of each process) |
| Release Work Order · Delete Master Plan · Enter new Current ETD | Planner | Master Plan · Plan Details (Release Work Order, Update ETD) |
| Create Work Orders per Big Plan · Send WOs to I/J Plan · Create NEW plans for processes with a Plan · Restore SO line Remaining · Build Reschedule Preview · Apply new schedule · Save Simulation | System (auto) | Master Plan (Preview Reschedule, Apply Reschedule, Save as Simulation) |
| # | Output | Produced when |
|---|---|---|
| O-2 | Plan = RELEASED; Work Orders (one WO per Big Plan, created at Create Plan, NOT RELEASED; P.O Month = Plan Month) carrying the chosen Routing turn RELEASED → I/J Plan, each WO one Detail Plan with the Master Plan number, grouped by I/J into an I/J Big Plan by Style + Model + Base Color + Plan Month + Area; Order Q'ty = WO Q'ty incl. Common Stock — + plan NEW for Trimming / Spray Out / Packing (per the WO's Routing) + Common Stock (the surplus). The Injection WI is not created here — it is created when scheduled on Injection Schedule | Plan DRAFT, the Planner clicks Release Work Order (no approval step) |
| O-3 | SO line Remaining given back | Delete plan DRAFT |
| O-4 | No delete in Master Plan — handled in Work Order | Plan already RELEASED |
| O-5 | New Current ETD + rescheduled process dates (Frozen processes unchanged) | Planner clicks Apply Reschedule |
| O-6 | Simulation copy, live schedule unchanged | Planner clicks Save as Simulation |
| O-7 | Keep ETD and process schedule | Planner clicks Cancel in Reschedule Preview |
| Glossary | Meaning in this flow |
|---|---|
SO | Sales Order — each size is one line |
Internal Production Request | Internal request to produce, not tied to a customer order |
Plan qty | Quantity the Planner decides to produce for a line |
REMAINING | Quantity of the SO line still to be planned |
Big Plan (Master Plan) | Group of SO lines with the same Style + Model + Base Color + SPRAY/Logo + Area in one Master Plan; each Big Plan becomes one Work Order |
Area | Field of Master Data Country; the SO line carries the ship-to Country and the system derives the Area |
Plan Month · P.O Month | Production month the Planner picks for the whole Master Plan · month recorded on the WO, equal to the Plan Month, unchanged after Release |
SPRAY / Logo | Item attribute telling whether goods go to Spray or Logo printing — two different Routings, so it is part of the Master Plan grouping key |
Master Plan | Overall plan for one Plan Month; one Master Plan → n Big Plans → n Work Orders |
Work Order (WO) | Production order, created for each Big Plan when the Master Plan is created (NOT RELEASED), released when the Master Plan is released; its status in Master Plan follows the whole Routing: NOT RELEASED → RELEASED → IN PROGRESS → COMPLETED |
Routing | The item's process sequence; defaults from Routing Mapping |
Lead Time · Buffer Days | Days per process · buffer days before the next process |
Common Stock | Surplus not tied to any SO line = Plan qty − total SO allocation |
Capacity Calendar | Daily machine / work center capacity, used for Over capacity warnings |
Current ETD | The plan's current estimated delivery date |
Frozen | A process with actuals, never rescheduled automatically |
Simulation | A saved trial reschedule that does not change the real schedule |